Monday, April 16, 2012

Foundation dry and temporary electric roughed in

Super productive weekend... On Friday, (Friday the 13th!) I cleaned the remaining dry mud from the bedrock and was very pleasantly surprised by how uniform, level and blemish free the bedrock looks. The block and mortar was delivered by Menard's by an enormous boom-truck and placed down in the hole for installation later. On Saturday, we were able to set-up the temporary electric service pole, meter box and wire for hook-up from Hancock-Wood Electric.
Block and mortar delivery

Bedrock clean and dry

Temporary electrical service on pole