Birthday weekend fast approaching
Looking forward (as usual) to going to the island this weekend. Bonnie and I will be heading up early Saturday morning to work on the site as well as spending some much needed time together. I am excited to show her the progress that has been made so far. The temporary electric service has been turned on, so we will finally have power. Also, the block guys may start laying the foundation depending on availability and weather. More to come!
Monday, April 16, 2012
Foundation dry and temporary electric roughed in
Block and mortar delivery
Bedrock clean and dry
Temporary electrical service on pole
Wednesday, April 11, 2012
All good in the hood
We were able to open up Cedar Cottage and all mechanicals worked as expected the weekend of Mar 30th - Apr 1st. The mild winter certainly helped as nothing seemed to be damaged as a result of freezing or excessive water exposure. I was able to make progress on the Lower Cliff property by draining the three-foot-deep foundation pond down to less than 1/4 inch of wet mud using 2 pumps for ~12 hours. Heading back up to continue site work on Friday, Apr 13th. See ya on the rock!
Pipe contraption that I hooked up to move water from the foundation pond
Water down > 12" since starting the pump(s)
Next morning, looking much drier!