This was the year of the new cottage construction on Southaven. I'll have memories and stories to tell for a lifetime getting this project off the ground (literally). Thanks to everyone who helped make this dream possible for me and the family.

We did get that full house HVAC completed on 11/22/19. Just in the nick of time.


Here is the outside of this beautiful baby as of 11/24/19.


Last photo of 2019. Interior is all set to be finished in Spring of 2020.


Stay tuned!

Sunday, November 17, 2019

Plumbing rough-in approved

Not a super exciting weekend. I did get the plumbing inspection approved by Erie County.


I also worked on hard piping in the sump pipe. Unfortunately, the pump I was using had finally died. So I'll bring up a new one for next weekend and wrap-it up.

I don't have any photos of this but we did get Hancock Wood to permanently hook up electric service. This is great and a big step. I was able to finally remove the temp service pole and extension cords from the yard. 

Sunday, November 3, 2019

Electric for now

This weekend, Derek and Joe came up to finish electrical in the garage and crawlspace. Plus they got the panel ready for a few receptacles and the rest to be shut off until next season. 



Here is a photo of the upstairs current state. Looks solid for now.