Sunday, October 27, 2019

HVAC install started

This week Tin Man Heating & Cooling (AIR-EEZ) started the whole house HVAC install. Hard to tell from the photo below, but this is a massive Carrier unit!




I started to frame out the bar for the party garage as well as mount the speakers for tunes.



Sunday, October 20, 2019

Crawlspace door

I built out the crawlspace door from pressure treated deck wood complete with some stylish black hardware to dress it up.


This is a the septic leach field repair job completed by Big Tim and Winston after the inadvertent breach last weekend by the trenching job. 



Neil and Soph came up for the family Halloween festivities this weekend. These photos were taking while waiting for the ferry at sunset.





Saturday, October 12, 2019

Ditch Witch

This weekend we rented a massive trencher (Ditch Witch) to dig all the infrastructure runs for:
  1. Electric (3 inch conduit)
  2. Water (3/4 direct burial PEX)
  3. Septic (3 inch PVC)
  4. Gutter (4 inch drain) 
We finished tasks 1-3. The gutter drains will be deferred until 2020.

Water line

Tim - Ditch King