Monday, August 26, 2019

August wrap-up

Big load from Olmsted Twp all the way to the island

Got the tub roughed in

Sunday, August 18, 2019

Monday, August 12, 2019

Framing and siding complete!

After about a six week delay, Tom and his crew were able to make it to the island for a day to finish the siding and trim. Also, we decided to add two windows to the kitchen.

Big Tom and crew


Cutting the framing, sheathing and siding for the windows rough-in



Inside kitchen view - so much more natural light!

View from back to show new kitchen windows

Here is the outside front view finally finished!

Tom, Dennis and crew

Friday, August 9, 2019

Garage door

Sometimes it's the little things...

Garage door finally installed

Sunday, August 4, 2019

Plumbing and insulation started

Not super exiting, but progress continues...

Insulation loaded - ready to roll to island

My girl!

Pex runs in the ceiling

More pex runs

Manabloc progress

Tuesday, July 30, 2019

July progress

Random July updates while we wait for the outside work to be completed.

Truckload of drain pipe ready for the island

Backfill looking good

Master bathroom rough PEX

Start of the PEX runs

Big Tim pulling romex

Lil Neil cleaning up for $5

Neil - backfill/back of house

Neil on the Bobcat

Monday, July 15, 2019

Kinda slowed down

Still waiting on the special order to finish the outside siding and trim. I started working on hanging receptacles for outlets and installed the pex manifold for plumbing supply lines.