Tuesday, May 15, 2012

Framing started!

After 11 months of planning, re-planning, and more re-planning, the builders started framing yesterday around noon. By early evening the floor joists and sub-floor were completed - moving right along. The crew is super fortunate to have great weather expected for the rest of the week. My daughter Sophie and I are making a quick mid-week run up to the island to deliver the front door and roof skylights. But the best part is that we can check the progress and hopefully get a peek at the fully framed cottage structure...

This is drainage hole/ditch that I had to dig by hand. That was a real pain-in-the-azz. Remind me to avoid hand digging in the future. However, it was absolutely necessary to have a solid 40' run of 4" drain pipe to tie in the sump pump and gutter downspouts.

Here is the asphalt primer I applied in preparation for the foundation membrane.

This is me working on the foundation membrane. Slow and messy. The plan is to keep the foundation and crawlspace as dry as possible!

Plywood for the sub-floor.

The crew installed I-joists which are manufactured floor joists that simplify construction, reduce cost and use 40-50% less wood than conventional floor joists. This should make the green environmentalists happy... 

Floor joists and sub-floor almost done. Here you can see the temporary sump pump plumbing that was tied into the drain pipe installed earlier.

Tuesday, May 8, 2012

Island sunset

Every day we get one step closer to the cottage being built and I am thankful for all of the great things I have been blessed with in my life. Check out this sunset from the south side of the island.


Monday, May 7, 2012

The foundation situation!

I am absolutely beaming over the fact that the foundation was completed this weekend. Actually, crew was done by 12:45 pm on Saturday afternoon. The plan was for them to be sitting at the bar by 1:00 pm and they kept to the schedule. Sam (from Marblehead) was a phenomenal mason - great price and outstanding quality work. I would highly recommend him to anyone needing concrete work in the area.

Day one - setting the first course on the bedrock.
No need for footer due to natural glacial smoothing less than one inch off level - amazing!

Day two - three walls done, moving along...

Day two - foundation complete!
Floor clean and temporary sump pump installed.

Done. Beer time. View from neighbor's cottage.

Wednesday, May 2, 2012

Slowly but surely

Bonnie and I had a fabulous weekend up on the island. We managed to get a lot of work done despite the rain. This upcoming Friday, our block layer is supposed to start working the corners of the foundation. The plan is to have all complete by end of day Saturday, weather permitting. Too busy to post any pictures. Next time for sure!

Monday, April 23, 2012

Birthday weekend fast approaching

Looking forward (as usual) to going to the island this weekend. Bonnie and I will be heading up early Saturday morning to work on the site as well as spending some much needed time together. I am excited to show her the progress that has been made so far. The temporary electric service has been turned on, so we will finally have power. Also, the block guys may start laying the foundation depending on availability and weather. More to come!

Monday, April 16, 2012

Foundation dry and temporary electric roughed in

Super productive weekend... On Friday, (Friday the 13th!) I cleaned the remaining dry mud from the bedrock and was very pleasantly surprised by how uniform, level and blemish free the bedrock looks. The block and mortar was delivered by Menard's by an enormous boom-truck and placed down in the hole for installation later. On Saturday, we were able to set-up the temporary electric service pole, meter box and wire for hook-up from Hancock-Wood Electric.
Block and mortar delivery

Bedrock clean and dry

Temporary electrical service on pole

Wednesday, April 11, 2012

All good in the hood

We were able to open up Cedar Cottage and all mechanicals worked as expected the weekend of Mar 30th - Apr 1st. The mild winter certainly helped as nothing seemed to be damaged as a result of freezing or excessive water exposure. I was able to make progress on the Lower Cliff property by draining the three-foot-deep foundation pond down to less than 1/4 inch of wet mud using 2 pumps for ~12 hours. Heading back up to continue site work on Friday, Apr 13th. See ya on the rock!

Pipe contraption that I hooked up to move water from the foundation pond

 Water down > 12" since starting the pump(s)

Next morning, looking much drier!